Despite Royce's intentions for the waterfall model to be modified into an iterative model, use of the "waterfall model" as a purely sequential process is still popular, and, for some, the phrase "waterfall model" has since come to refer to any approach to software creation which is seen as inflexible and non-iterative. Those who use the phrase waterfall model pejoratively for non-iterative models that they dislike usually see the waterfall model itself as naive and unsuitable for a "real world" process.

The best-known and oldest process is the waterfall model, where developers (roughly) follow these steps in order:

Process activities/steps

To follow the waterfall model, one proceeds from one phase to the next in a purely sequential manner. For example, one first completes "requirements specification" — they set in stone the requirements of the software. When the requirements are fully completed, one proceeds to design. The software in question is designed and a "blueprint" is drawn for implementers (coders) to follow — this design should be a plan for implementing the requirements given. When the design is fully completed, an implementation of that design is made by coders. Towards the later stages of this implementation phase, disparate software components produced by different teams are integrated. After the implementation and integration phases are complete, the software product is tested and debugged; any faults introduced in earlier phases are removed here. Then the software product is installed, and later maintained to introduce new functionality and remove bugs.

Thus the waterfall model maintains that one should move to a phase only when its preceding phase is completed and perfected. Phases of development in the waterfall model are thus discrete, and there is no jumping back and forth or overlap between them.

There is a misconception that the process has no provision for correcting errors in early steps (for example, in the requirements). In fact this is where the domain of requirements management comes in which includes change control.

This approach is used in high risk projects, particularly large defense contracts. The problems in waterfall do not arise from "immature engineering practices, particularly in requirements analysis and requirements management." Studies of the failure rate of the specification, which enforced waterfall, have shown that the more closely a project follows its process, specifically in up-front requirements gathering, the more likely the project is to release features that are not used in their current form.

More often too the supposed stages are part of joint review between customer and supplier, the supplier can, in fact, develop at risk and evolve the design but must sell off the design at a key milestone called Critical Design Review (CDR). This shifts engineering burdens from engineers to customers who may have other skills.

The waterfall model however is argued by many to be a bad idea in practice, mainly because of their belief that it is impossible to get one phase of a software product's lifecycle "perfected" before moving on to the next phases and learning from them (or, at least, the belief that this is impossible for any non-trivial program). For example, clients may not be aware of exactly what requirements they want before they see a working prototype and can comment upon it; they may change their requirements constantly, and program designers and implementers may have little control over this. If clients change their requirements after a design is finished, that design must be modified to accommodate the new requirements, invalidating quite a good deal of effort if overly large amounts of time have been invested into "Big Design Up Front". (Thus, methods opposed to the naive waterfall model--such as those used in Agile software development--advocate less reliance on a fixed, static requirements document or design document). Designers may not (or, more likely, cannot) be aware of future implementation difficulties when writing a design for an unimplemented software product. That is, it may become clear in the implementation phase that a particular area of program functionality is extraordinarily difficult to implement. If this is the case, it is better to revise the design than to persist in using a design that was made based on faulty predictions and that does not account for the newly discovered problem areas.

Get Jobilize Job Search Mobile App in your pocket Now!

Get it on Google Play Download on the App Store Now




Source:  OpenStax, Software engineering. OpenStax CNX. Jul 29, 2009 Download for free at http://cnx.org/content/col10790/1.1
Google Play and the Google Play logo are trademarks of Google Inc.

Notification Switch

Would you like to follow the 'Software engineering' conversation and receive update notifications?

Ask